Difference between revisions of "Labs Sessions - 2018"
From Green Garage Detroit
(→Labs Session - May 4, 2018) |
|||
Line 110: | Line 110: | ||
* '''What's Next''' | * '''What's Next''' | ||
** Cave Day - LLC out of commission on 5/18 | ** Cave Day - LLC out of commission on 5/18 | ||
+ | ** Next Month | ||
+ | |||
+ | ---- | ||
+ | |||
+ | ====Labs Session - June 1, 2018==== | ||
+ | * '''Labs Updates''' | ||
+ | ** Results finalized for '''[[TRASH AUDIT- April 2018]]''' | ||
+ | *** Turn over to Matt/businesses | ||
+ | *** Labs follow up with [http://www.recyclehere.net/index1.html Recycle Here!] (Matt Niemi) - date for field trip | ||
+ | ** GG Ventilation Project Update - select date | ||
+ | *** Finish Phase 2 Rebalance - Exhaust/Return Duct TAB Optimization | ||
+ | *** Balance Dampers installation status Annex - Joey G | ||
+ | **** Register in Red Panda has integral damper; use that to try to direct more air from the lg conf rm. | ||
+ | *** Plan for "Off Hours" Rebalance of Exhaust (Saturday in June or July) | ||
+ | *** Final Readings on Ventilation System | ||
+ | *** Phase 3 Remaining Issues on Ventilation (if any!) | ||
+ | ** [https://www.egauge.net/commercial-energy-monitor/#overview eGauge Power Monitoring] at El Moore - Unexpected loads on non-HVAC electric meter - pending | ||
+ | *** Domestic Water Booster | ||
+ | *** Elevator | ||
+ | *** Data analysis forthcoming | ||
+ | ** GG PV System Verification - future potential verification | ||
+ | *** Review new PV system design & specs - original GG [[PV System Design]] | ||
+ | *** [https://enlighten.enphaseenergy.com/systems? ENPHASE Monitoring] | ||
+ | *** Verification plan - Put data logger on PV produced vs feed to building to compare amps used | ||
+ | ** [https://www.weatherlink.com/bulletin/dce99048-2b67-4e1a-902a-216845e15ca7 GG Weather Station] - Davis VantagePro2 weather station with a Radiation sensor | ||
+ | *** Status of monitoring - no update since 4/26/2018 - Nate out of country | ||
+ | *** Commissioning verification of station as installed | ||
+ | *** Long term plan for station - Tom | ||
+ | |||
+ | * '''What's Next''' | ||
+ | ** Cave Day | ||
** Next Month | ** Next Month | ||
Revision as of 16:28, 1 June 2018
Home of the MADD Scientists - "Making A Difference Daily"
return to Sustainability Labs
go to Labs Highlights
go to Labs Sessions - Q1 2015
go to Labs Sessions - 2016
go to Labs Sessions - 2017
GG Labs Sessions are held the first Friday of each month after the Community Lunch, starting at 2:00 p.m. and ending around 4:00 p.m. All are welcome!!
Contents
Labs Sessions - 1st Quarter 2018
Labs Session - Jan 5, 2018
- Labs Updates
- Catching Up
- 2018 LABS Topics
- 1) Finish Up Phase 2 Rebalance and Phase 3 Remaining Issues on Ventilation
- 2) GG PV System Verification
- Review new PV system design & specs - original GG PV System Design
- ENPHASE Monitoring
- Verification plan - Put data logger on PV produced vs feed to building to compare amps used
- 3) Re-Commission the HVAC DDC Controls (after Niagara/JACE upgrades)
- Today's Project: Ventilation Update & Cold Weather Review
- Ventilation Update
- Review progress & results
- Summarize 12/15/17 readings/results
- Set date to re-read all at once - 1/12/2018
- Determine if BF needs to be set lower to match ERV?
- Determine if SF & EF on ERV are okay as is or need to adjust speed to get in balance?
- Plan for Cave Day
- GG Cold Weather Review
- Check systems; capture screenshots
- Review system cold weather performance; collect trends for past 2 weeks
- Thermal image doors/windows/floor/tank town walls/etc.
- Review observations
- Doors and windows still look very good, even high traffic doors.
- Exterior door in greenhouse is only spot found that is below the space dewpoint (door wood inset/threshold in 20's; dewpoint 36F).
- Garage door insulation/seal still excellent.
- Observed V-6 (three-way mixing valve on floor heating) appeared to be hunting slightly. Joe indicated this is normal for the valve.
- Consider any additional investigation or recommendations - none
- What's Next
- Cave Day - Continue Re-Do of TAB measurements
- Next Month - Wrap up Ventilation
Labs Session - April 6, 2018
- Labs Updates
- Catching Up
- Today's Project: TRASH AUDIT- April 2018
- Trash Audit Design
- Check current compliance levels
- Analyze current waste stream content compared to what it was
- Issue #1 - Lots of carry out cartons now - CONFIRMED STILL AN ISSUE
- Issue #2 - Food left in fridge on Friday - CONFIRMED STILL AN ISSUE
- First audit was 11/4/2011
- After Action: Talk to Recycle Here to solicit feedback on what we could do better or if anything new in the world of recycling
- After Action: Drill down to hear what we do right/wrong once it gets to the sorting process or its final destination - update us on what helps and what doesn't - what ruins a stream or makes it unusable
- Conclusions - Suggestions
- Businesses to address findings further
- Labs interested in community aspects of findings
- What's Next
- Cave Day
- Next Month
Labs Session - May 4, 2018
- Labs Updates
- Finalize results report for TRASH AUDIT- April 2018
- Merge report and photos - LLC2
- Turn over to Matt/businesses
- Labs follow up with Recycle Here! (Matt Niemi) - date for field trip
- GG Ventilation Project Update - select date upon Helen return
- Finish Phase 2 Rebalance - Exhaust/Return Duct TAB Optimization
- Balance Dampers installation status Annex - Joey G
- Register in Red Panda has integral damper; use that to try to direct more air from the lg conf rm.
- Plan for "Off Hours" Rebalance of Exhaust (Saturday next month; check with Helen upon return)
- Final Readings on Ventilation System
- Phase 3 Remaining Issues on Ventilation (if any!)
- eGauge Power Monitoring at El Moore - Unexpected loads on non-HVAC electric meter - pending
- Domestic Water Booster
- Elevator
- Data analysis forthcoming
- GG PV System Verification - future potential verification
- Review new PV system design & specs - original GG PV System Design
- ENPHASE Monitoring
- Verification plan - Put data logger on PV produced vs feed to building to compare amps used
- GG Weather Station - Davis VantagePro2 weather station with a Radiation sensor
- Status of monitoring - no update since 4/26/2018 - Nate out of country
- Commissioning verification of station as installed
- Long term plan for station - Tom
- Finalize results report for TRASH AUDIT- April 2018
- What's Next
- Cave Day - LLC out of commission on 5/18
- Next Month
Labs Session - June 1, 2018
- Labs Updates
- Results finalized for TRASH AUDIT- April 2018
- Turn over to Matt/businesses
- Labs follow up with Recycle Here! (Matt Niemi) - date for field trip
- GG Ventilation Project Update - select date
- Finish Phase 2 Rebalance - Exhaust/Return Duct TAB Optimization
- Balance Dampers installation status Annex - Joey G
- Register in Red Panda has integral damper; use that to try to direct more air from the lg conf rm.
- Plan for "Off Hours" Rebalance of Exhaust (Saturday in June or July)
- Final Readings on Ventilation System
- Phase 3 Remaining Issues on Ventilation (if any!)
- eGauge Power Monitoring at El Moore - Unexpected loads on non-HVAC electric meter - pending
- Domestic Water Booster
- Elevator
- Data analysis forthcoming
- GG PV System Verification - future potential verification
- Review new PV system design & specs - original GG PV System Design
- ENPHASE Monitoring
- Verification plan - Put data logger on PV produced vs feed to building to compare amps used
- GG Weather Station - Davis VantagePro2 weather station with a Radiation sensor
- Status of monitoring - no update since 4/26/2018 - Nate out of country
- Commissioning verification of station as installed
- Long term plan for station - Tom
- Results finalized for TRASH AUDIT- April 2018
- What's Next
- Cave Day
- Next Month
Labs Session - x x, 2017
- Labs Updates
- Catching Up
- Today's Project:
- Prep - Overview
- Hands-On
- Brain Work
- Conclusions - Suggestions
- What's Next
- Cave Day
- Next Month
Cave Day Items
- Commissioning Items
- ENERGY - Tracking energy produced vs. used
- ON-GOING Cx - using DDC for monitoring & persistence
- Labs Experiments
- WASTE - Kirsten's Waste Watch
- BCS - Cooling & Dehumidification M&V on coil
- BCS - Trickle loop experiment
- ENERGY - Phase 2 - Finish documentation on refrigerator electrical usage and performance
- [1] Solar Oven - example
- CURRENT CAVE DAY FOCUS
- Holdovers from 2015
- Trickle Loop Experiment
- Earth Room Performance (efficiency) number crunching; is Earth Room bypass viable; optimize Earth Room exhaust fan
- BCS - Annex revised ductwork and airflow readings
- BCS - Building pressurization by balance - summer/winter modes
- Holdovers from 2015
END OF LIST
Resources
- Commissioning Design Center
- Labs Highlights
- Labs Help Wanted
- Current Labs Summary
- Labs Idea Bin
- Labs Tool Box
- Labs As-Builts
To Do
- Plan / Do / Check / Act / Repeat
- 2018 LABS Topics
- TBD