August 30, 2009

We started with a ceremonial removal of the first brick on August 30th.

Joe removing the first brick



September 4, 2009

Removing old insulation from above the suspended ceiling and placing it into a temporary room. The insulation will be used again in another area of the Green Garage. The work was done by Kenco Company.


September 9, 2009