== September 30, 2009 ==
 +
Some views of the deconstruction. New scale to weigh outgoing materials. Volunteers and visitors.
 +
 +
<gallery>
 +
Image:ceiling-east-9-30.jpg|the view looking up and east
 +
 +
Image:ceiling-west-9-30.jpg|the view looking up and west
 +
 +
Image:looking-down-9-30.jpg|looking down at Tom pulling nails
 +
 +
Image:greg-9-30.jpg|Greg pulling nails
 +
 +
Image:scale.jpg|we found a scale to weigh outgoing materials
 +
 +
Image:visitors-9-30.jpg|Nicky and Somer from CCS taking the tour
 +
 +
</gallery>
 +
 +
 +
== October 2, 2009 ==
 +
This week the interior front windows were removed, and more volunteers worked on removing nails.
 +
<gallery>
 +
Image:jamilah-10-2.jpg|Jamilah removing nails
 +
 +
Image:inside-10-2.jpg|the inside of the building
 +
 +
Image:wood-10-2.jpg|wood waiting for nail removal
 +
 +
Image:don-mike-10-2.jpg|Don and Mike removing nails
 +
 +
Image:jamilah-2-10-2.jpg|Jamilah removing nails
 +
 +
Image:windows-down-10-2.jpg|windows coming down
 +
 +
Image:windows-down-2-10-2.jpg|windows coming down
 +
 +
</gallery>
 +
 +
== October 14, 2009 ==
 +
This week the parapet (a wall that stands higher than a roof) was disassembled out front.
 +
<gallery>
 +
Image:inside-10-14.jpg|the inside of the building
 +
 +
Image:inside-bricks-10-14.jpg|bricks stacked up
 +
 +
Image:front-10-14.jpg|taking apart the parapet outside
 +
 +
Image:parapet-10-14.jpg|a closer view of the parapet
 +
 +
Image:view-across-street-10-14.jpg|the view from across the street
 +
 +
Image:inside-heladio-10-14.jpg|Heladio working on deconstruction
 +
 
</gallery>
 
</gallery>
  

Latest revision as of 18:21, 14 October 2009

return to Main Page

August 30, 2009

We started with a ceremonial removal of the first brick on August 30th.

Joe removing the first brick



September 4, 2009

Removing old insulation from above the suspended ceiling and placing it into a temporary room. The insulation will be used again in another area of the Green Garage. The work was done by Kenco Company.


September 9, 2009

We had to begin working in the addition to get away from all the noise and dust, so we set up a work area there. The materials are coming off the walls and are being taken for storage to the addition.

September 16, 2009

We hired Eduardo Martinez to do the bulk of the deconstruction work. He started with the walls. When the wood was removed, Tom O'Connor and others (like Steve Lambers, pictured) removed nails so we could use the wood again.


September 22, 2009

After the walls, we wanted to remove the suspended ceiling. First, though, we had to remove the bulk of the old insulation that lay on top of the panels. So we hired Kenco to come in and suck out the insulation. Instead of taking it to a landfill, however, we asked them to come up with a way to store it in the building so we could use it later when we start adding insulation to the remodeled building. They developed a plastic-lined room and found a way to pipe the insulation in. These were loud days at the Green Garage. (But it worked).


September 25, 2009

Updated views of the interior as it is being deconstructed.


September 30, 2009

Some views of the deconstruction. New scale to weigh outgoing materials. Volunteers and visitors.


October 2, 2009

This week the interior front windows were removed, and more volunteers worked on removing nails.

October 14, 2009

This week the parapet (a wall that stands higher than a roof) was disassembled out front.