City of Detroit Approval Process
From Green Garage Detroit
Revision as of 20:16, 11 June 2009 by Tom Brennan (Talk | contribs)
Historical
- Called Susan McBride on 06/11/09 about getting on the Historic District Commission Agenda
- Next Historic Commission Meeting is on July 8th; materials due June 22nd
- Materials include:
- Letter explaining project
- 1 large set of plans and 1 11x17 set of plans
- Site plan
- Elevations
- Materials
- Planting plan
- Window brochure
- Any digital photo's
- Met with Susan McBride at her office (about February 2009)
- covered preliminary plans
- Met with Susan McBride at Green Garage (about October 2008)
- covered our concept and what the Historic Commission requires
Building
- Met with Jim Sears (Building) on 06/11/09
- Jim said that "your adding an office to a warehouse"
- Paid $1,160 ($160 for plan review and $1,000 for BZA)
- Ref #'s:
- SLU 2009-00109
- PRV 2009-00417
- TAG 02888
- Sent the plans on to John for Site Plan review
- Then they go to the BZA for review and scheduling
- They'll call Ted with updates
- Met with Jean Paul (Planning and Zoning) and Bill Lane (Building)..(in early May 2009)
- Covered basic building use and plan.
- Currently approved for warehouse and storage use.
- Bill said everything looked good except parking...which needs to go to BZA