City of Detroit Approval Process

From Green Garage Detroit
Revision as of 20:16, 11 June 2009 by Tom Brennan (Talk | contribs)

Jump to: navigation, search

Historical


  • Called Susan McBride on 06/11/09 about getting on the Historic District Commission Agenda
    • Next Historic Commission Meeting is on July 8th; materials due June 22nd
    • Materials include:
      • Letter explaining project
      • 1 large set of plans and 1 11x17 set of plans
        • Site plan
        • Elevations
        • Materials
        • Planting plan
        • Window brochure
      • Any digital photo's

  • Met with Susan McBride at her office (about February 2009)
    • covered preliminary plans

  • Met with Susan McBride at Green Garage (about October 2008)
    • covered our concept and what the Historic Commission requires

Building


  • Met with Jim Sears (Building) on 06/11/09
    • Jim said that "your adding an office to a warehouse"
    • Paid $1,160 ($160 for plan review and $1,000 for BZA)
    • Ref #'s:
      • SLU 2009-00109
      • PRV 2009-00417
      • TAG 02888
    • Sent the plans on to John for Site Plan review
    • Then they go to the BZA for review and scheduling
    • They'll call Ted with updates

  • Met with Jean Paul (Planning and Zoning) and Bill Lane (Building)..(in early May 2009)
    • Covered basic building use and plan.
    • Currently approved for warehouse and storage use.
    • Bill said everything looked good except parking...which needs to go to BZA